six men can complete a certain work in 20 days .how many men are required to complete the same work in 12 days ?

Respuesta :

AvelL99591 AvelL99591
  • 25-10-2022

6 men complete the work in 20 days.

In 1 day it takes:

6 x20 = 120 men

You need to do the same work done in 20 days, in one day. (more manpower)

So, to finish the work in 12 days:

120 men / 12 days = 10 men

Answer Link

Otras preguntas

it's generally recommended that athletes consume approximately____ percent of their daily calories?
What is x2 -6x-23=0 using square roots
Geometry  The diagonals of a  kite are in the ratio of 3:2. The area of the kite is 27 cm^2 .  Find the length of both diagonals. (Hint: Let the lengths of the
Which of the following tends to form a cation (positive ion) with a charge of 2+? a. Na b. O c. He d. Mg
what did fascists believe was necessary to achieve order in a society
How did America end up going to War with Iraq?
Multiplying a number by 2 and then adding 5 gives the same number as subtracting a number from 23. What is the number?
When organisms must compete for resources, they will usually have a ____________ distribution. a. uniform b. random c. clumped d. competitive
How are boundaries between river systems and natural vegetation regions different?
without multiplying determine which expression has a product greater than 52,678A) 5/6 x 52,678B) 9/9 x 52,678C) 4/3 x 52,678D) 3/5 x 52,678How can I tell just