Resource leveling is a network scheduling technique that seeks to assign nearly equivalent work units to each member of the project team True False

Respuesta :

Emhicee
Emhicee Emhicee
  • 26-01-2020

Answer:

False

Explanation:

Resource leveling in project management is a technique used to ensure that over-allocation of resource or conflicts as a result of over-allocation does not occur.

Cheers

Answer Link

Otras preguntas

You bought a shirt at regular price for $27 and a pair of jeans that are marked $68 but are 25% off. How much will you pay with tax (8.25%)? Round to the neares
A recycling truck picks up 4535 kilograms of cardboard from the grocery store round the weight of the cardboard to the nearest hundred
This is from the book "Restart". PLZ HELP ME A. Identify four of Chase Ambrose's internal character traits. B. Support each chosen character trait with proof fr
identify whether the sentence blows were written in an active or passive voice the national anthem was sung by Carrie at the late nights basketball game. in the
can you also include how you solved it(;´༎ຶٹ༎ຶ`)
please help me quickly
Write the expression using exponents (-2) • (-2) • (-2) • 3 • 3• 3(-2) • (-2) • (-2) • 3 •
Watch your mouth! CROSSWORD PUZZLE
Someone help me with this question pls
The molar volume of a gas increases by a factor of two. Which parameter change could have cause the shift in molar volume