You work as a project coordinator for a design company. on one project, the status report shows that 10 of the work was completed in 90 days. if the work progresses at the same rate, how many days will be required to complete the remainder of the project?
a. 9 days
b. 80 days
c. 100 days
d. 810 days

Respuesta :

Otras preguntas

The legendary figure Narmer is famous for being
Name a product for which all eight marketing functions do not need to be performed by someone somewhere in the marketing system. Explain your thinking about wha
The capital of the Ghana Empire was _____. Jenne-jeno Timbuktu Kumbi Saleh Jenne
Flatworms are capable of reproducing sexually or by _____. budding fragmentation reverse osmosis
Over time, the snow in a glacier becomes more and more _____. A. fluffy B. white C. dense D. slippery
A plants response to light is known as A. phototropism. B. gravitropism. C. thigmatropism. D. heliotropism.
why do we have 3 branches of government
Who was the communist leader of Cuba during the Cuban Missile Crisis?
There was separation of church and state in the Massachusetts Bay Colony. a. True b. False
only question one for now thanks